Eastcroft Walkways and Lighting

Design, supply and install upgrade works for EMR at Eastcroft depot

Customer

EMR

Date Completed

March 2026

Sector

Rail Infrastructure

Project Overview

Eastcroft Upgrade Works

Download the case study here

EMR appointed Cairn Cross to update the existing infrastructure and bring it into full compliance with current standards, with a focus on improving safety, accessibility, and visibility across the depot. The works comprised the design, supply, and installation of a 145LM GRP walkway complete with integrated LED strip lighting along its full length. In addition, LED lighting was installed to the drip tray throughout the main shed to enhance footpath visibility.

As part of the compliance upgrades, non-compliant handrails were removed and replaced with 45LM of compliant GRP handrails. The project also included the modification and extension of an existing GRP walkway to Road 14, ensuring a cohesive and fully compliant access solution.

 

Project Details

Services delivered included:

  • GRP Walkways
  • GRP Handrails
  • LED Lighting

Eastcroft Walkways and lighting
01.

The Challenge

The project demanded meticulous planning from initial design through to procurement and delivery, all within a tight programme and a constrained depot environment. This required precise coordination, rigorous control, and careful programme management to ensure successful delivery.

Eastcroft Walkways and lighting
02.

The Solution

Strong communication with the client, shunter control, and on-site teams was critical to success. Detailed site surveys were undertaken, and clear mapping was produced to support planning and execution.

A structured procurement schedule ensured all materials were delivered to site in a timely manner, avoiding delays. Labour, plant, and tools were also carefully planned and coordinated to align with the programme and site constraints.

Eastcroft Walkways and lighting
03.

The Result

The project was delivered seamlessly, with all works completed safely, on time, and within budget.
The upgraded walkway and lighting have significantly improved visibility, safety, and compliance within the depot.

Due to site constraints, all waste materials were efficiently managed and transferred to Etches Park Depot.
Cairn Cross successfully delivered safe, compliant, and efficient rail infrastructure solutions at Eastcroft, effectively navigating a challenging environment and programme.