Todwick Road Bridge Deck Replacement

Working as a specialist subcontractor, Cairn Cross helped deliver the deck replacement on behalf of Ringway.

Customer

Ringway

Date Completed

2007

Sector

Highway, Bridges & Structures

Project Overview

Working as a specialist subcontractor, Cairn Cross helped deliver the deck replacement on behalf of Ringway.


Bridge Construction Todwick Road Cairn Cross
01.

The Challenge

The project was to replace the Todwick Bridge deck with new road construction and associated safety measures.

Over Railway Bridge Resurfacing Civils Works
02.

The Solution

To carry out the work, in-situ reinforced deck construction took place on-site to maximise efficiency. Concrete Omnia planks were placed as permanent soffit during the weekend rail possessions. Abutments were also pre-cast on site adjacent to the bridge location and lifted in by crane during rail possession times. New parapet support system tie rods encapsulated the construction deck before kerbs and drainage were installed.

Todwick Road new bridge road construction
03.

The Result

A newly renovated two-way road bridge deck replacement complete with diaphragm walls and parapets.